Friday, August 15, 2008

reFraming

The bumpout is up on crutches, but it’s better and stronger than ever before! The jacks lifted it back inline, and the sag is gone


<-- Check out the underside.There's a new 2x10 sistered onto each joist from the edge of the bumpout through to the super-beefy beam running down the center of the garage.

It feels much more stable there too, walking and jumping on it from above. And soon we can get back to stapling up the heating fins so sometime this winter we have a chance of having heat. It'll be much easier to get the fins and tubing out under the bumpout with the underside exposed like this.

<-- These are those joists from the inside. You can see a bit of daylight coming through at the ends, and the sistered joists are resting on our super-beefy garage beam.

You can also see one set of window openings framed in with the new header and post.

Here’s a better view of the window framing in the garage/workshop.

The openings have new 6x6 headers, which are supported in the middle by 4x6 posts


This is the window framing in the bedroom in back.. there's actually wall back there now!

Which makes it reeeaally dark in there.. this pic is blindly taken with the flash. If only we had some windows..

Thursday, August 14, 2008

the Wall, continued

Here we have the beginning of the sheathing.

The windows you see there leaning up against the house are from the garage.. they don't match any other windows in the house and because they’re double-wides we had some problems with the framing that needed fixing.

From the inside a couple days ago you can see what the problem with the header is.. there isn't one! There's just a couple 2x6s turned on their side.. Not sure if you can see the sag in this picture, but it's pretty pronounced.

To span the opening over 2 windows with two stories above, we would have to put in a pretty beefy header, which would mean moving the windows down and buying new expensive beams. The alternative is to split up the windows and put a supporting post in between to support the header in the middle, which is what we decided to do.

Another issue we need to address is that the bumpout is underframed, and sagging even worse since the foundation was done. We figured it would be much better to deal with that now, before we closed up the walls. So we need to sister 2x10s to all the joists that cantilever out in the bumpout.

Here you can see the supports in place to prop it back up to level. Next, the joists can be attached nice and straight-like

Monday, August 11, 2008

the Wall

The East wall of the house has been a bit of a problem, particularly the outside wall of the downstairs bedroom. Between the 2 falling apart windows, and the “windows” that are essentially panes of glass somehow suspended midway up the wall, and the door opening we got rid of, there's pretty much no wall there anyway.

There's nothing to do but rebuild the wall from scratch, which of course means up to all modern codes with shear wall and housewrap and flashing.. so we talked a lot about what we should do with the rest of the wall towards the front of the house. Although it wasn’t a cost we weren’t expecting now, the obvious best thing for the house in the long run is to sheath and waterproof the whole length of the wall. We had a pile of 2x6s from an old project (which I spent HOURS moving from a pile out back to a pile along the side of the house.. but that’s not a very exciting blog post), which made a huge dent in the materials we had to purchase for this.

Another issue is that, because of all the openings in the outside wall of the bedroom in back, there is very little siding longer that a foot or two long. Short of having custom siding milled to the thickness and profile of the original siding, there would be a bunch of work to shim out anything we could buy off the shelf to line up with the original siding at the front of the house, and it would not be likely to wind up seamless, even with all that effort.. Ultimately, we decided to use the new siding we bought for the back of the house (which, conveniently enough is still sitting on sawhorses smack in the middle of the garage in the way of everything we try to do down there) and get more of it to replace everything along the wall with the new stuff. The original siding will be perfect for the back of the house.. we have enough long runs to do most of it, and the short runs will be fine for what’s hidden behind the stairs.

Once we decided all that, we were stuck with a decision on doing it ourselves over the next several months, or hiring someone who could get it done well in a fraction of that time. Dan interviewed at least a dozen contractors, and found a local team that came very highly recommended, sounded like they knew what they were talking about, and who does excellent work.
(Note to one of the contractors we talked to.. if you fail your contractor's exam A) do NOT bring that up in an interview, and B) if you happen to let it slip, you might want to consider charging slightly less than what a licensed contractor would get)

So, they got started today and should be done in about a week

Check out the new use of our former plywood backdoor!

Saturday, August 2, 2008

New windows

Our new windows are here!

I'll explain more about why we bought the windows as we go into the impending framing in the house, but the price of these was also a factor in buying new instead of trying to fix and move the old ones.

Plus, I read all the time about how windows are the one thing that you want to buy new instead of salvaging from old houses.. The performance and efficiency of double-pane windows are far beyond the old single-paned ones.

We went with Marvin Integrity Wood-Ultrex series windows, which seem pretty great.. They're clear pine on the inside, paintable fiberglass clad on the outside (I know that we'd never have to paint them if we just got them clad in a color we want for the trim on the house.. we're just not beige people..), with low E insulated glazing.

And somehow, because they only come in a handful of sizes, they're really affordable. So, as you can see, we loaded up ;)

Tuesday, July 29, 2008

Pretty door stuff

I somehow totally missed posting pictures of the gorgeous hinges doing their gorgeous thing!

<-- And look, they hold the door up too! The doorjambs are also very pretty, made from douglas fir, so when we finally get around to staining and sealing them they'll match the doors perfectly.

And in the meantime, we've got some knobs!

It's funny.. I was just getting used to having the deadbolts in place, so now after I unlock the door I keep pushing on it, expecting it to open, and thinking it must still be locked somehow. And then I finally remember to turn the knob and everything works just like it should. I must be tired, because I keep doing that..

<-- This is the unfinished, interior fire door. The reproduction privacy sets have a fake keyhole cut in them which I love! That little detail is why I bought the knobs from Nostalgic Warehouse instead of one of the dozen or so places online that carry similar hardware.

I was planning on drilling it out so you could actually see though the door, but I think I'm going to paint that spot black instead.. at least to start off with.. I can always drill a hole later if it looks weird.


Sorry for the lack of posting recently.. it's been a bunch of behind the scenes stuff and some non-house related work which I'll post some pix of soon

Thursday, July 24, 2008

we're lousy with doors!

Just look at all the doors we have now!!
<--This one you can see from the street! You can also see the old, rotty door leaning against the house.. guess we'll have to something with that.. Anyone need a fine, antique door? it's cheap! ;) Still not much in the way of doorknobs.. but there's a functional lock, which opens with a key, on each and every external door we have! (not counting the piece of plywood covering the hole where there used to be a door.. any minute now there's going to be a wall there instead, so I'm counting that as wall, not door)

<-- This is the firedoor between the garage and the living space. We didn't have the space in our "clean room" to stain and seal it with the others, and since it was prehung because it needed special self-closing hinges we figured it'd be just as easy to finish it once it was up.

We have to finish all the jambs anyway, so there's about a million more coats of varnish in my future.


<-- And this is the firedoor between the living space and the garage.

It's the same door.. It's just so exciting I thought I'd show it from both sides :D

Monday, July 14, 2008

it takes one to.. get another one

Now that we've got one door, it seems like the others might be willing to go up too..

This is the door jamb for the back door. You can just kinda see the really fracking gorgeous hinges there..

One of the conditions Zach had for helping us with these doors was that we get them as slabs (not pre-hung) because that was where all the fun and challenge is!

Here is that piece and the rest of the jamb in place at the back doorway.

Notice the utter lack of plywood back there?? Any minute now there's also going to be a lock with a key instead of a sliding latch that we can only get to from the inside. Don't get me wrong, the plywood with latch was a vast improvement over the gaping hole, and is much better than a screwed-on inoperable piece of plywood.

The 2nd half of "fun and challenging," getting the door to swing freely and close all the way.

And the really fun part! A closed door!! With a lock on it, even. A lock that we have keys for!

The doorknob will come soon, and then it will be just like a real door!

There's way more light in that area now too. There aren't any windows back there, which is why we got the door with lights on top, and it makes a really big difference.

We still have to stain and seal the jamb, and there's the slight lack of siding there which will have to be addressed before we can trim the door out.. but I'm enjoying the fact that (have I mentioned this yet?) there's totally a door back there :D